We're renewing the playground at Hagger Park, Woolooware

Hagger Park, WOOLOOWARE - near the Railway Station.

Project timeline

Project start: Construction will start in September 2024

Expected completion:  December 2024

Project scope

We will replace the existing playground with new modern equipment.
The work will include:

  • New playground equipment including climbing, sliding, swinging and nature play elements
  • New carousel spinner
  • Mixture of synthetic and natural softfall material
  • New access path, seating and water station
  • Landscaping

Work hours

Monday to Friday 7.00am to 5.30pm, and occasional Saturday work between 8.00am and 1.00pm.

No work will take place on public holidays.

We will keep you updated as the work progresses and thank you for your patience.