Hawkesbury Esplanade and corner of Moruya Ave, SYLVANIA WATERS.
Project timeline
Project start: Aug 2024
Completed: 1 Nov 2024
Project scope
We will replace the existing playground with new modern equipment.
The work will include:
- New Access ramp to play equipment
- New junior and senior playground equipment, including climbing, sliding, swinging elements
- Mixture of synthetic and mulch softfall material for play areas
- Renewal of concrete around the existing barbeque and seating areas
- Minor landscaping