We are building a new accessible play space adjacent to the Leisure Centre within Waratah Park.
Waratah Park - Rawson Parade, Sutherland.
Project timeline
Project start: Nov 2024
Expected Completion: Jun 2025
Project background
The new playground in Waratah Park at Sutherland aligns with the Masterplan for this precinct, which was adopted by Council in April 2022. This is an important and diverse regional recreational facility and the Waratah Park Masterplan provides a coordinated and long-term approach to the way open spaces and recreation opportunities are improved into the future.
This play space will provide a vibrant and inclusive recreational facility that enhances the social and visual qualities of the area and will offer a unique play experience. The playground design celebrates the distinctive local character of Waratah Park and is accessible from the parking area and community bus stops.
It will have safe, level and well-lit pedestrian connections to Rawson Avenue and reflects the importance of this regional recreation area within the Waratah Park precinct.
Consultation with our community
Council consulted with the local community and stakeholders about the Waratah Park Masterplan between February and November 2021. Your feedback informed the development of detailed design elements for the new playground. Find out more here.
Scope of works
The current work includes:
- Drainage works
- Retaining wall to improve the grade
- New lighting
- Pedestrian pathway connections
- Perimeter fencing
- Feature trees in a variety of species
- New All-ability amenities building
Our exciting new All-abilities play equipment will include:
- A flying fox with accessible seat
- Sand and water sensory play
- Accessible carousel and slides
- Swings with different seat options
- Junior bike path
- Musical and nature play
- Seating and shaded social areas
Media Release
MON 25 NOV 2024 - New Playground to deliver fun in spades as Councillors 'dig in' to kickstart construction
Project schedule
Community Consultation for Masterplan – February to November 2021 (complete)
Adoption of Masterplan - April 2022 (complete)
Concept Design – December 2023 (complete)
Detailed Design – August 2024 (complete)
Site Establishment – mid November 2024
Estimated Practical Completion – June 2025
Public impacts during construction
The site area will be closed for public use during the construction period.
Normal access to the Leisure Centre will be uninterrupted.
Funding
This project is funded by Sutherland Shire Council from the Developer Contribution Plan.
Frequently Asked Questions
Development of the masterplan was supported by an extensive, multi-stage consultation program to ensure that the final plan reflected community feedback and current and future recreation needs.
Council’s Urban Tree & Bushland Policy requires that Council undertake offset planting as part of any project in which trees are removed. For each tree that is removed, four trees will be planted as a replacement.
The design allows for plenty of natural shade within the all-abilities play area. Additional shade structures are incorporated over specific elements.
The new all abilities playground at Waratah Park is designed in keeping with the NSW Everyone Can Play Guidelines and offers play spaces that are welcoming and comfortable for everyone. It will provide a variety of challenging and engaging play opportunities regardless of age, ability or interest.