Project timeline
Project start: Jan 2025
Expected completion: end of Mar 2025
Project background
Oval drainage upgrades are important to ensure the longevity and playability of sports field surfaces and to ensure the continuity of sporting competitions throughout the season. This will improve the amenity of the open space for our whole community to enjoy an active lifestyle.
Project scope
The work includes:
- Provision of an automatic irrigation system.
- Localised improvements to subsoil drainage system.
- Minor turf remediation for drainage works.
Project schedule
Detailed Design - November 2024 (complete)
Tender - December 2024 (complete)
Site Establishment – end of January 2025
Practical Completion – end March 2025 (weather permitting)
Impacts during construction
The playing field will be closed during construction. We appreciate the support and collaboration of our sport clubs and local user groups during this process.
We will keep you updated as the work progresses and thank you for your patience.
Funding
This project is fully funded by Council.